Posted by: tiniantimes | September 28, 2010

Indonesia ENCAPS: The Island of Ambon

The Island of Ambon:

  • Puskesmas Tulehu Public Health Clinic

This small isolated clinic is located about an hour outside the city of Ambon. Though the clinic was open, the building was in dire need of repair. The staff moved out of the building during the renovation, and aided the Seabees in cleaning and moving back in when completed.

PROJECT SCOPE: Install a new corrugated metal roof and ridge cap; replace the existing wood fascia; repair exterior soffit framing and replace damaged soffit. Replace all damaged ceiling panels; replace the existing front and rear doors with new solid wood doors and new locksets; replace two interior doors and install one new frame; replace 18 door lock sets on existing doors; remove five exterior doors and fill openings with masonry brick and stucco. Remove wood slats above new rear double door and fill with plywood; replace wood slats above all windows; create new slats above one closed-in door for ventilation; do minor electrical repairs and replace missing light bulbs. Prep and repair all interior and exterior stucco walls, then prime and paint the entire building inside and out. Remove dirt and debris from sidewalk around building and power-wash all concrete walks, including the main walk to the font of the clinic. Replace damaged tile floors throughout the clinic; pour a new concrete step at the rear of the clinic.

The front of the clinic before

The front of the building after

The side of the building before

The side of the building after (notice the brand-new roof!)

Picture showing the before and after side-by-side

This picture shows the concrete block used to fill-in doors that were removed

Reception area before

Reception area after (Senior Chief VanGorden wants you to notice the large stash of LDS Charity boxes filled with medical supplies that were given to the clinic during the ribbon-cutting ceremony–typical of ALL ENCAP projects!)

Central hallway before

Central hallway after

The Seabees pose in front of the newly renovated clinic

PERSONNEL: 11 SAIL-IN Seabees and 16 ROYAL Australian ARMY engineers; 8 Host Nation VOLUNTEERS; 15 Mercy  Volunteers

DURATION: 25 JUL 2010 – 30 JUL 2010

MAN-DAYS EXPENDED: 125


  • Tulehu Toilet Facility, Ambon

This small project was developed and begun by the local TNI engineers on the island. The Seabees were asked to aid in completing as much work as possible during their visit.

PROJECT SCOPE: Aid the Host Nation Engineers to build a new toilet facility. Mercy Seabees aided in the following work: run fresh water lines to toilets; run sewer lines from toilets; build a stone and concrete foundation, then stucco-covered brick walls; frame a wood roof and install corrugated metal roofing; install doors; and install squat toilets.

New toilet facility being worked on (the toilets drained out the back into the waterway, and down into the ocean)

Toilet facility almost completed

Typical Asian squat toilet, with faucet to fill bucket for flushing the toilet

PERSONNEL: 3 SAIL-IN Seabees and 2 ROYAL Australian ARMY engineers; 3 Host nation engineers

DURATION: 25 jul 2010 – 30 JUl 2010

MAN-DAYS EXPENDED: 31


  • Mamala Stage, Ambon

This project was part of a larger renovation of a local soccer field. The local TNI engineers on the island were building a stage at one end of the field. The Seabees were asked to aid in completing as much work as possible during their visit.

PROJECT SCOPE: Aid the Host Nation Engineers to build a new stage. The Seabees from Mercy aided in constructing concrete walls atop a poured concrete foundation in preparation for installing a new roof.

The new stage was being built near the local Soccer Stadium

The stage as the concrete beams were being installed to hold-up the roof

PERSONNEL: 2 SAIL-IN Seabees and 3 ROYAL Australian ARMY engineers; and 4 host nation engineers

DURATION: 27 JUL 2010 – 28 JUL 2010

MANDAYS EXPENDED: 14

The City of Ambon Pier problem…

Not everything goes perfect on a mission as large and complex as this one. While delivering supplies from the USNS Mercy to the pier in Ambon, the helicopter being used caused some damage to a nearby warehouse.

The Mercy helocopter making a supply run to the pier

The roofing structure and roof of the building had not been secured to the surrounding masonry walls… When the helocopter landed, the ‘updraft’ from the spinning blades lifted the unattached roof right off the building! The Navy met with the owner of the building and came to an agreement very quickly… Fortunately the warehouse was completely empty at the time of the incident.


Advertisement

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Connecting to %s

Categories

Follow

Get every new post delivered to your Inbox.